EGESIM’S REFERENCES IN GEOTHERMAL POWER GENERATION SYSTEMS

ENDA TUZLA GEPP / CANAKKALE – TURKEY (2010)

  • The plant has 7,5 MW power capacity & produces 51.000.000 kWh yearly.
  • BOP ( Balance of Plant ) Electrical & Automation system.
  • System Software & SCADA, Engineering, Assembly, Production & Commissioning

♦ MAREN SINEM and DENIZ GEPP / AYDIN – TURKEY (2012)

  • 2×24 MW Geothermal Energy Power Plant Electrification
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation (2X S7 – 419H CPU)
  • Turbine Cubicles, Switchgear, complete Plant Electrification
  • MV Cubicle network integration
  • System Software & SCADA, Engineering, Assembly, Production & Commissioning

♦ MAREN KEN3 & MEHMETHAN GEPP / AYDIN – TURKEY (2016)

  • 2×24 MW Geothermal Energy Power Plant Electrification
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation (PCS7 CPU 410-5H)
  • Turbine Cubicles, Switchgear, complete Plant Electrification
  • MV Cubicle network integration
  • 154 kV 28 / 35 Mva Transformer Feeder Primer – Seconder Installation, Tests & Commissioning
  • System Software & SCADA, Engineering, Assembly, Production & Commissioning
  • FEED PUMP Panels
  • MV Cubicle network integration
  • Engineering & Installation & Supervising & Commissioning
  • Getting approvement of the projects from Ministry of Energy

MELİH  GEPP (Continued)

  • 154kV 28/35 MVA transformer feeder Primary-Secondary installation,Test and Commissioning
  • 1X24 MW Geothermal Energy Power Plant Electrification
  • BOP (Balance of Plant) Energy Scada Automation, process automation PCS7-CPU 410-5H)
  • Turbine cubicles, Switchgear, complete powerplant electrification
  • MV Cell network entegration
  • Engineering&Installation&Supervision&Commissioning

♦ CELIKLER PAMUKOREN 1 & 2 GEPP / AYDIN – TURKEY (2013)

  • 2×24 MW production capacity
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation
  • 6×400 kW Sinamics G130 Drive Systems
  • Process Control Equipment
  • MV Cubicle network integration
  • Engineering & Installation & Supervising & Commissioning,
  • Getting approvement of the projects from Ministry of Energy

♦ CELIKLER PAMUKOREN 3 & 4 GEPP / AYDIN – TURKEY (2015)

  • 2×24 MW production capacity
  • 154 kV 70 MVA Transformer Feeder Primer-Seconder Installation, Tests & Commissioning
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation
  • 6×800 kW 690 VAC Sinamics G130 Drive Systems
  • Process Control Equipment
  • ORC MCC Panels
  • FEED PUMP Panels
  • MV Cubicle network integration
  • Engineering & Installation & Supervising & Commissioning
  • Getting approvement of the projects from Ministry of Energy

CELIKLER PAMUKOREN 5 GEPP / AYDIN – TURKEY (2015)

  • Total 22,5 MW production capacity
  • 154 kV 70 MVA Transformer Feeder Primer-Seconder Installation, Tests & Commissioning
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation
  • 3×800 kW 690 VAC Sinamics G130 Drive Systems
  • Process Control Equipment
  • ORC MCC Panels
  • FEED PUMP Panels
  • MV Cubicle network integration
  • Engineering & Installation & Supervising & Commissioning
  • Getting approvement of the projects from Ministry of Energy

♦ CELIKLER SULTANHISAR GEPP / AYDIN – TURKEY (2016)

  • Total 12,5 MW production capacity
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation
  • 5X800kW 690VAC Sinamics G130 Drive Systems
  • Process Control Equipment
  • ORC MCC Panels
  • Engineering & Installation & Supervising & Commissioning,
  • Getting approvement of the projects from Ministry of Energy

♦ GURMAT EFELER 1 GEPP / GERMENCIK – AYDIN – TURKEY

  • Commissioning of fire detection and suppression system
  • Installation & Commissioning of CCTV system, its integration with automation system

GURMAT EFELER 2 GEPP / GERMENCIK – AYDIN – TURKEY (2014)

  • Total 22,5 MW production capacity
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation (Redundant PCS7 CPU 416 -5H)
  • PCS7 System and PCS7 Software and Network Integration
  • MV Cubicle network integration, Sivacon S8 Panels
  • Engineering & Installation & Supervising & Commissioning

♦ GURMAT EFELER 3 GEPP / GERMENCIK – AYDIN – TURKEY (2014)

  • 154 kV 28/35 MVA Transformer Feeder Primer-Seconder Installation, Tests & Commissioning
  • Total 22,5 MW production capacity
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation (Redundant PCS7 CPU 416 -5H)
  • MV Cubicle network integration, Sivacon S8 Panels
  • Engineering & Installation & Supervising & Commissioning

GURMAT EFELER 4 GEPP / GERMENCIK – AYDIN – TURKEY (2015)

  • 154 kV 28/35 MVA Transformer Feeder Primer-Seconder Installation, Tests & Commissioning
  • Total 22,5 MW production capacity
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation (Redundant PCS7 CPU 416 -5H)
  • PCS7 System
  • MV Cubicle network integration, Sivacon S8 Panels
  • Engineering & Installation & Supervising & Commissioning

♦ GURMAT EFELER 6 GEPP / GERMENCIK – AYDIN – TURKEY (2016)

  • 154 kV 28/35 MVA Transformer Feeder Primer-Seconder Installation, Tests & Commissioning
  • Total 22,5 MW production capacity
  • BOP(Balance of Plant) Energy Scada Automation, Process Automation (Redundant PCS7 CPU 416 -5H)
  • PCS7 System
  • MV Cubicles Network Integration,
  • Engineering & Installation & Supervising & Commissioning

GURMAT (EFELER 7) GEOTHERMAL POWER PLANT (Continued)

  • Total power output 22.5MW
  • BOP (Balance of Plant) Energy Scada Automation, Process Automation (PCS7 CPU 416-5H)
  • MV Cell network integration
  • Engineering & Installation & Supervision & Commissioning 2018

♦ MTN ENERGY – TUZLA GEPP / CANAKKALE – TURKEY (2015)

  • 7,5 MW Energy Station, Complete Electrification
  • BOP (Balance of Plant) Energy Scada Automation
  • PCS7 CPU 414-5H redundant Automation network design, engineering, installation, supervising commissioning
  • MV Cubicle network integration
  • ORC MCC Panels
  • Getting approvement of the projects from Ministry of Energy

♦ KARKEY UMURLU 1 GEPP / AYDIN – TURKEY (2015)

  • 12,5 MW Energy Station, Complete Electrification
  • BOP (Balance of Plant) Energy Scada Automation
  • PCS7-400H redundant Automation network design, Engineering & Installation & Supervising
  • 12,5 MW Energy Stations, ORC Automation Panels and MCC Panels
  • 12,5 MW Energy Stations, BOP Automation Panels and MCC Panels
  • 12,5 MW Energy Stations, MV Panels

♦ KARKEY UMURLU 2 GEPP / AYDIN – TURKEY (2016)

  • 12,5 MW Energy Station, Complete Electrification
  • BOP (Balance of Plant) Energy Scada Automation
  • PCS7-400H redundant Automation network design, Engineering & Installation & Supervising
  • 12,5 MW Energy Stations, ORC Automation Panels and MCC Panels
  • 12,5 MW Energy Stations, BOP Automation Panels and MCC Panels
  • 12,5 MW Energy Stations, MV Panels

♦ GREENECO BUHARKENT GEPP / DENIZLI – TURKEY (2015 – 2016)

  • 2×12,5 MW Energy Station, ORC Automation Panels
  • LV Sivacon S8 Distribution Panels (PHASE I – PHASE II)
  • LV Sivacon S8 VFD Panels (8×200 kW)

♦ ENERJEO ENERGY – KEMALIYE GEPP / MANISA – TURKEY (2016)

  • 12,5 MW Energy Station (PHASE-I & PHASE II) ORC Automation Panels and MCC Panels
  • 12,5 MW Energy Station (PHASE-I & PHASE II) Generator Protection and Control Panel (GCPP-I – GCPP-II)
  • 12 kV MV Panels, protection and control
  • Double Front Sivacon S8 Withdrawable Panels
  • LV Sivacon S8 VFD Panels (6 x 250 kW)
  • PHASE II – 2 ORC Automation Panels
  • CRIP, VHP, RIW, WHR Panels, Sivacon S8
  • Engineering & Installation & Supervising & Commissioning

♦ KARIZMA KUBILAY GEPP / AYDIN – TURKEY (2016)

  • 1×24 MW Geothermal Power Plant Electrification and installation
  • 154 kV Switchgear and 154 kV Overhead Line Projecting, Engineering, Equipment and Installation services
  • Drilling Platform electrical works 450 + 710 kW motor supply, Driver panels, LV and MV Panels production, installation and commissioning
  • Supply and installation works of basic earthing equipment of the plant.
  • BOP (Balance of Plant), Energy Scada Automation, Process Automation PCS7 CPU 410-5H) and installation
  • MV Cubicles network integration
  • Engineering, Installation, Supervising & Commissioning
  • Getting approvement of the projects from Ministry of Energy

♦ SIS ENERJI – OZMEN-1 GEPP / MANISA – TURKEY (2016)

  • 1×24 MW Geothermal Power Plant Electrification and installation
  • 154kV Switchgear Equipment supply, projecting, engineering and installation works
  • Supply and installation works of basic earthing equipment of the plant.
  • LV and MV switchgear fabrication, installation commissioning
  • BOP (Balance of Plant), Energy Scada Automation, Process Automation PCS7 CPU 410-5H) and installation
  • MV Cubicle network integration
  • Engineering & Installation & Supervising & Commissioning

♦ MASPO ENERGY – ALA-1 GEPP / MANISA – TURKEY (2016)

  • 1×10 MW Geothermal Power Plant Electrification and installation
  • Earthing design, material procurement and installation
  • LV and MV switchgear fabrication, installation commissioning
  • 3X560kW MV switchgear fabrication, installation commissioning

♦ TURCAS ENERGY – KUYUCAK GEPP / AYDIN (Continued)

  • Plant foundation earthing, procurement and installation works
  • Production and assembly of LV and MV Switchgears, Commissioning 2017
  • Electrification and installation of 1×18,16 MW geothermal power plant
  • Engineering & Installation & Supervision & Commisioning 2017
  • Ministery Approval  and E.T.K.B. approval for projects

♦ 3S KALE ENERGY  / AYDIN (Continued)

  • 154kV switchgear procurement, Project , engineering and intallation works

♦ LİMGAZ JEOTERMAL ELEKTRİK ÜRETİM A.Ş. / AYDIN (Continued)

  • 13,4 MW Capacity on EPC base turnkey projects
  • Engineering, Design and Drawings
    • Including Production Wells, Pipe Lines, ORC Power Plant, Reinjection Pipe Line and Reinjection Wells:

Civil Works

  • Topographic Study,
  • General Layout including ORC Plant, Gathering, BOP and Roads
  • Foundation Drawings
  • Electrical Main buiding
  • Administrative Building
  • Warehouse and Storage Building with overhead crane
  • Pressurized Air Prep. Building
  • Motive Fluid storage area
  • Gathering Emergency Pond with sump pumps
  • Roads and environmental arrangements including surface water drains
  • Gardening

Mechanical Works:

  • ORC,
  • Gathering
  • BOP

Electrical and Automation Works:

  • 154Kv- 18 MVA Switchyard
  • BOP (Balance of Plant) Energy Scada and Process Automation
  • Process Control Equipment
  • ORC MCC Panels
  • Feed Pump Panels
  • MV Cells Network Integration
  • Transformers
  • Complete Plant electrification
  • Supply of Material and Equipment
  • Constructional Works
  • Erection and ınstallation
  • Assembly Works
  • Test, Start up and Commissioning
  • Documentation
  • Quality assurance
  • Maintenance planning and Preparation of Spare Parts List
  • Long Term Service Agreement (LTSA)
  • Approval of Drawings and Ministy Acceptance