Egesim has successfully started up 7 Geothermal Energy Stations (2 Switchgears)

EGESIM, providing innovative engineering ideas and high technologies to Geothermal Energy Stations, has successfully started up 7 Geothermal Energy Stations  (2 Switchgears) on the same date (31.10.2016 ).

KARIZMA 154 kV Power Transmission Line, 154/11 kV Switchgear were started up and accepted by the Ministry of Energy on 31.10.2016.

MAREN Energy Mehmethan 154 kV Power Transmission Line, 154/31,1 kV Switchgear were started up on 31.10.2016. On the same date 24 MW Maren Mehmethan and Ken-3 Geothermal Energy Stations were started up.

The following plants were accepted by the Ministry of Energy on 31.10.2016:

  • Maren Energy Ken-3 Geothermal Energy Station  24 MW
  • Maren Energy Mehmethan Geothermal Energy Station  24 MW
  • Celikler A.S. Sultanhisar Geothermal Energy Station  12 MW
  • Karizma Energy Bestepeler Geothermal Energy Station  24 MW
  • Karkey Umurlu Geothermal Energy Station  12 MW